Highway 75 Planners Discuss Key Intersections, Pedestrian Routes

Concept drawing of street intersection

Safety and function are driving planning for several important pieces of Sioux Center’s Highway 75 redesign. This week, the City Council discussed several significant design details as the community moves toward the highway reconstruction in 2023-24. 

Trent Bruce, of DGR Engineering, shared a design update with the council, highlighting intersections, pedestrian routes, and traffic patterns. 

One intersection receiving attention is 16th Street SW, which links Highway 75 to the commercial area to the west. The proposed design includes additional lanes on that block of 16th Street, preparing for growth in traffic in that area as it continues to develop. 

“When we started to look at the design, we felt that we needed to look at this more wholistically,” Bruce said. “The design we were working with, just at the intersection, was not really set up for future development as you would expect for the area west of the highway.”

Safe pedestrian routes and paths continue to be a focus. The design includes 10 pedestrian crossings with rapid-flashing beacons planned and five crossings at traffic signal intersections. Bruce shared that one crossing had been moved from 5th Street South to 4th Street South based on public feedback, with people requesting that a crossing be available at 4th Street near Bethel Christian Reformed Church.

One traffic pattern that may change as part of this project is related to the Post Office’s drop boxes. Currently the boxes are just off Highway 75, but they may move to the back of the post office property to be accessible off of 1st Ave East. This proposed change has yet to receive final approval.

Bruce also reviewed the project timeline with the council. He reported that the right of way process with the DOT contacting property owners will likely happen later this fall or early in 2022, a bit later than anticipated. Final design will continue through summer of 2022, and bid letting is set for January 2023. Construction is anticipated in 2023-24, likely between April 1 to mid-November of those years, and project completion is set for 2025.

Facebook Twitter Email

Other News in City News

fireworks

Using Fireworks in Sioux Center

Posted on: May 25, 2023
Drawing of hotel exterior

Agreement Assists Development of New Hotel

Posted on: February 27, 2023
Concept of detention pond

New Detention Pond Will Benefit Community

Posted on: February 21, 2023
Map of road construction project

First Highway 75 Bids are Favorable

Posted on: February 2, 2023
Lifeguard watches pool from chair

All Seasons Center Rates Adjusted for 2023

Posted on: December 12, 2022
Concept for reconstruction of road

City Prepares for Highway 75 Replacement

Posted on: December 3, 2022
Man's face and drawing of buildings

Gonzalez Begins as Building Code Official

Posted on: September 1, 2022
New Office Hours sign

City Office Hours Change on August 22

Posted on: August 16, 2022
top of tree

Local Response to Emerald Ash Borer

Posted on: March 3, 2022
Softball Field with players lined up

Softball Diamond Named Field of Excellence

Posted on: February 17, 2022
Woman at table with three children

State Awards Grant for Childcare Project

Posted on: February 15, 2022
Inside an indoor turf dome

Indoor Turf Sports Complex Moving Forward

Posted on: November 24, 2021
Three adult faces

Sioux Center Elects Council Members

Posted on: November 9, 2021
Work crew preparing basement for cement

Heritage Village Begins Historic Move

Posted on: October 28, 2021
Fire station

Fire Station 2 Open House on Oct. 7

Posted on: September 24, 2021